Project Background:
A high-speed road section in Anhui, China, urgently needs to build a highly reliable, easy-to-maintain and space-saving back-end support environment for key road condition monitoring, information dissemination, tolling system and communication network. The traditional decentralised server room construction faces challenges such as space constraints, long deployment cycle, complex operation and maintenance, and low energy efficiency.
Customer Requirements:
Server room needs to ensure 7×24 uninterrupted operation of high-speed key services, adapt to the requirements of the motorway project schedule, and meet the space constraints of the server room along the motorway.
Solution:
GOTTOGPOWER provides a prefabricated, modular GT integrated data centre solution, which includes: integrated high-density UPS uninterruptible power supply system, energy-efficient precision air-conditioning, and integrated intelligent cabinets to reduce the space occupied.
The project has been successfully deployed and put into stable operation.
The successful practice of the Expressway project once again proves the excellent adaptability and reliability of GOTTOGPOWER’s integrated data centre solution in the field of transportation critical infrastructure.